Comment
Core Strategy Preferred Approaches
Representation ID: 439
Received: 24/07/2008
Representation Summary:
ESCC flood risk analysis fell short of the Environment Agency's requirements and an addendum is due. Throughout the plans I have concerns that the drain off from the road (H&B link road) plus the change in the land could impact on the areas south of the road. There seems to be a lack of consideration for this in the ESCC plans.