Comment

Core Strategy Preferred Approaches

Representation ID: 1485

Received: 08/07/2008

Representation Summary:

The strategic importance of the Bexhill-Hastings Link Road (BHLR) is evident throughout the document, but its implementation is not yet secure & no alternative or contingent strategy is offered should the BHLR fail to materialise. This may be regarded as questionning the soundness of the Plan when submitted. Furthermore, the documents estimated completion date of the BHLR of autumn 2011 is now looking slightly optimistic. The document (para 18.5) also needs to reflect the role of the BHLR in opening up strategic housing & employment sites in North Bexhil.